Bradford Sanitary Authority
Bradford Sanitary Authority (BSA) provides wastewater treatment for several municipalities including the City of Bradford, along with Bradford and Foster Township. It operates a wastewater treatment plant with two process trains (Activated Sludge & SBR) as well as a collection system and the related stormwater system.
Beginning in the Spring of 2011, Mr. Book began his involvement with the Authority in support of the PennVEST funding by completing a Second Opinion Project Review (SOPR) package on the preliminary design prepared by Gannett Fleming, Inc.This report included questions and suggestions, which lead to the ultimate final design which was bid in 2014 and placed into operation in late 2016.
In February 2017, Brian was again hired to provide operations support and expert witness consulting on the issues associated with the Contract Closeout of the Construction Project.
In March 2018, cb3 Solutions, LLC was hired to continue this work of Operations Consulting and Expert Witness Testimony. The details are confidential.
In October 2021, we were hired to evaluate options to improve the SBR Decant Control System.